The FDOT’s US-1 Bike Lane Widening project has begun. The project will widen the existing bike lanes from 3 feet to 5 feet from Sample Road north to the Broward County / Palm Beach County line. It also includes new pavement, pavement markings, various sidewalk repairs and ADA sidewalk ramp improvements. The project shrinks the medians in US-1 by 2 feet on both sides to gain the necessary space to widen the bike lanes.
Construction activities associated with the widening will take place Monday through Friday, from 7 am to 5 pm.
Median modifications in the City of LHP are nearing completion. Sidewalk modifications and repairs will commence upon median completion. Present project complete date is April, 2021.
UPDATE: Milling and resurfacing operations continue. TWO-LANE CLOSURE North and Southbound at various times scheduled for weeks beginning 02/22/2021 and 3/1/2021.