Please see attached public notice regarding the upcoming installation of Phase 5 for COPB’s Oasis Reclaimed Water program. The project is scheduled to begin as early as next Wednesday, 04/24, with staging and materials delivery. Pipe installation is scheduled to begin the following Monday, 04/29. Project duration is estimated at 14 weeks. There are no scheduled road closures but there will be intermittent lane closures in the construction areas. Updated 4/17/2024